The installation site of concrete batch plant

The following is the installation of our customer HZS60 concrete mixing plant in Philippines, and let me see the installation process together.

Feeding system installation: the finished material conveyor from bending, the frame on the basis of the connection before and after the frame, then the front and the rear leg and the conveyor connected, inclined and lug rack connected, then lift the front conveyor, connect the front and rear legs with the brace, the anchor bolts to tighten the front and rear legs.

The mixing hosting of concrete batch plant machine: the installation of mixing main machine and powder batching system, lifting the main machine frame, put it on the foundation, fastening the anchor bolt. The installation of the finished storage hopper will lift the storage hopper, erect the outrigger, and connect the walking platform and ladder with the material hopper. Aggregate batching system installed on the hoist aggregate batching system based on inserting plate connected, both sides will be connected with the heightening plate up plate, then the original aggregate conveyer, the front and the rear frame are connected, the electric drum mixer head cover alignment hole center, the anchor bolt fastening.

Cement silo installation: the cement silo parts which are assembled on the ground, lift cement silo, and toward the side of the capsule stents under lateral brace less powder batching system, fixed capsule, finally fixed anchor bolt.

Screw conveyor installation: lifting screw conveyor, screw conveyor to the spherical hinge and the cement silo outlet connected, a discharging mouth of the powder feeding hopper, and then use the rope to the conveyor and the cement silo with lifting lugs, the anchor bolt fixed.