Teach you five steps to install concrete batch plant

Teach you five steps to install concrete batch plant:

1, the installation of feeding system

Small concrete batching plant installation finished product installation will be finished product belt conveyor , from bending after framework on the basis, framework, before and after the connection is good then before and after leg good connection with conveyer, brace and rack lug connection is good, then the front of conveyor lift, fitting of front and rear leg and brace, finally the leg before and after the anchor bolts.

2, stirring the mixing host

the mixing host and the powder batching system to install the mainframe rack, on the basis of its anchor bolts to fasten.

3, the installation of finished ingredients warehouse

Finished storage hopper installation will be finished storage hopper lifting, the legs will stand up, will walk Taiwan, ladder and finished material storage hopper connected. The preparation of the pelletizing system is carried out on the basis of the above, the board will be connected, and the two sides will be put on the sides and the board will be connected with the card, and then the original aggregate conveyor will start, After the rear rack is connected, the electric drum is aligned with the center of the mixer head hole, and finally the anchor bolts are tightened.

4, the installation of the cement silo

Cement warehouse installation will cement warehouse parts which are assembled on the ground, lift cement silo, and toward the side of the capsule stents under lateral brace less powder batching system, fixed capsule, finally fixed anchor bolt.

5, the installation of screw feeder

Installation of screw conveyor Lifting screw conveyor, the screw conveyor ball hinge and cement warehouse outlet connection, so that the discharge port on the powder hopper feed port, and then use the rope to the conveyor and the cement warehouse hanging ear Well, finally fix the anchor bolts.